Project Development Weekly Progress Report #2
Süleyman Melih Portakal edited this page Oct 10, 2023
·
3 revisions
Team Name: Group 6 - Game Forum
Date: 10.10.2023
This week focused on making decisions to make our project domain-specific. We divided our teams for the back-end, the front-end, and the mobile. We decided on the main technologies that will be used. We couldn't make updates to the class diagram and the use case diagram. Our objective for the following week will be to updating requirements, use case, class and sequence diagrams. Also, learning technologies that we will use.
Description | Issue | Assignee | Due | PR | Estimated Duration | Actual Duration |
---|---|---|---|---|---|---|
Refactor the requirements | #238 | Team | 05.10.2023 | 5hr | 2hr | |
Update the use case diagram w.r.t. the changes in the requirements | #239 | Team | 06.10.2023 | 2hr | ||
Update the class diagram w.r.t. the changes in the requirements | #240 | Team | 06.10.2023 | 2hr | ||
Update the sequence diagram w.r.t. the changes in the requirements | #241 | Team | 06.10.2023 | 2hr | ||
Decide on what technologies are going to be used for the front-end | #242 | Front-Team | 06.10.2023 | 1hr | 0.5hr | |
Decide on what technologies are going to be used for the mobile | #243 | Mobile-Team | 06.10.2023 | 1hr | 0.5hr | |
Decide on what technologies are going to be used for the back-end | #244 | Back-Team | 06.10.2023 | 1hr | 0.5hr |
Description | Issue | Assignee | Due | PR |
---|---|---|---|---|
- We decided due date of refactoring requirements too short. However this task can take a few weeks more. We could't finished the task but we decided some requirements.
- We planned update the use case, class and sequence diagram. However, we spent so much time to make our project domain-specific. Therefore, we couldn't start updating.
Description | Issue | Assignee | Due | Estimated Duration |
---|---|---|---|---|
Deciding the design of the game page | #249 | Team | 17.10.2023 | 2hr |
Refactor the requirements | #238 | Team | 24.10.2023 | 2hr/week |
Update the use case diagram w.r.t. the changes in the requirements | #239 | Team | 24.10.2023 | 2hr/week |
Update the class diagram w.r.t. the changes in the requirements | #240 | Team | 24.10.2023 | 2hr/week |
Update the sequence diagram w.r.t. the changes in the requirements | #241 | Team | 24.10.2023 | 2hr/week |
Learn React framework for the front-end | #242 | Frontend-Team | 31.10.2023 | 2hr/week |
Learn Flutter framework to be used for the mobile | #243 | Mobile-Team | 31.10.2023 | 2hr/week |
Learn Spring Boot framework for the back-end | #244 | Backend-Team | 31.10.2023 | 2hr/week |
- Ahmet Kudu
- Beyzanur Bektan
- Emre Türker
- Erkam Kavak
- Halis Ayberk Erdem
- Hüseyin Çivi
- Muhammet Mustafa Küçük
- Ömer Bahadıroğlu
- Ömer Talip Akalın
- Süleyman Melih Portakal
- Umut Demir
- Ahmet Kudu
- Beyzanur Bektan
- Emre Sin
- Emre Türker
- Erkam Kavak
- Halis Ayberk Erdem
- Hüseyin Çivi
- Ömer Bahadıroğlu
- Ömer Talip Akalın
- Sena Özpınar
- Süleyman Melih Portakal
- Umut Demir
- Muhammet Mustafa Küçük
- Scenarios
- Mockups
- Meeting #1 - 03.03.2023
- Meeting #2 - 10.03.2023
- Meeting #3 - 12.03.2023
- Meeting #4 - 13.03.2023
- Meeting #5 - 19.03.2023
- Meeting #6 - 24.03.2023
- Meeting #7 - 26.03.2023
- Meeting #8 - 30.03.2023
- Meeting #9 - 02.04.2023
- Meeting #10 - 04.04.2023
- Meeting #11 - 05.04.2023
- Meeting #12 - 06.04.2023
- Meeting #13 - 07.04.2023
- Meeting #14 - 08.04.2023
- Meeting #15 - 09.04.2023
- Meeting #16 - 27.04.2023
- Meeting #17 - 30.04.2023
- Meeting #18 - 04.05.2023
- Meeting #19 - 07.05.2023
- Meeting #20 - 11.05.2023
- Meeting #21 - 05.10.2023
- Meeting #22 - 11.10.2023
- Meeting #23 - 16.10.2023
- Meeting #1 - 21.10.2023 (Backend)
- Meeting #1 - 22.10.2023 (Frontend)