Contributions of Ali Başaran ‐ 451
Name: Ali Başaran
Group: 5
Over the course of five weeks, I had various responsibilities in the project. Those responsibilities were mostly related to front-end the application, but I also contributed other fields of the project. My responsibilities were:
- As a communicator, communicating with the customer, understanding their requests and to transferring this information to the team members.
- Taking part of decision processes in front-end team, such as color palette decisions, library selections etc.
- Attending the meetings and taking notes if I am a note taker.
- Updating and redesigning requirements
- Implementing various parts in front-end such as implementing log out functionality of the web application and connecting the implemented web pages to the backend.
- Deploying the front-end of the application to an AWS server.
- Resolving bugs I encountered.
To sum up, I believe that I was an active member and I have contributed equally to the team's efforts, working on various implementation and documentation tasks.
Week 1
Description Type of Work Issue Time Spent Talking with the Customer and Sharing the Feedback on Communication Channels Documentation #374 2 hour Reviewing the Existing Repository Discussion #396 2 hour Attending Weekly Team Meeting #1 and adding the notes to the wiki Documentation #398 1 hour 30 mins Week 2
Description Type of Work Issue Time Spent Decide on Front-End Technologies Discussion #419 2 hours Decide on a component library for styling the front-end project Discussion #425 2 hours Update/Redesign our requirements Documentation #428 2 hours Create and Design a To Do List for Project Documentation #437 1 hour 30 mins Week 3
Week 4
Description Type of Work Issue Time Spent Review Game Page Web Mockups Discussion #460 1 hour Resolving the CORS Error Bug #491 2 hours Handling the Empty Submit in Forgot Password Route Bug #492 2 hours Deploy Frontend To AWS Feature #495 5 hours Determining the Primary, Secondary, Background, Text and Dark Text Colors Design #498 2 hours Resolving Login Page Email Field Bug Bug #566 1 hour Creating Release for Milestone 1 Documentation #596 30 mins Week 5
Description Type of Work Issue Time Spent Adding My Individual Contributions to First Milestone Deliverables Documentation #531 2 hours Updating the RAM Documentation #535 1 hour Preparing list and status of deliverables Documentation #545 2 hours Updating Communication Plan Documentation #619 15 mins
I have various code related contributions to the project but I believe that following four work is the most significant code related issues:
- Connecting Implemented Pages to Endpoints
- Deployment of the Front-End of the Application
- Implementing log out functionality
- Creating Release for Milestone 1
I have various management related contributions to the project but I believe that following four work is the most significant management related issues:
- Talking with the Customer and Sharing the Feedback on Communication Channels
- Creating and Design a To Do List for Project
- Updating Requirements
- Preparing list and status of deliverables
Title | PR | Conflict |
---|---|---|
Lab report #4 is added | #550 | |
Pulling Backend Auth Updates | #559 | |
Frontend connect to backend | #560 | |
Frontend/move services | #571 | I edited the implemented pages to connect them to backend. It caused conflicts. |
Minor Register Bug is Solved | #590 | |
Pulling the Updates from Main | #591 | |
Resend Code is Implemented | #592 | |
Unused Imports are Removed | #602 |
Title | PR |
---|---|
Update lab_report_2.md | #420 |
Frontend main layout | #476 |
_colors.scss added | #478 |
Frontend/favicon titles | #576 |
Frontend/game details | #583 |
Logout is added to topbar | #584 |
Title | PR | Conflict |
---|---|---|
Update lab_report_2.md | #420 | There were 2 lab report branches so reports were conflicted |
Frontend main layout | #476 | |
_colors.scss added | #478 | |
Frontend/favicon titles | #576 | |
Frontend/game details | #583 | |
Logout is added to topbar | #584 |
I regularly attended the classes, labs, team meetings and front-end team meetings. I tried to contribute as equal as my team members and I took various tasks to achieve my best.
Cmpe 352
Cmpe 451
Cmpe 352
Milestone 1
Final Milestone
Milestone 1
Milestone 2
Final Milestone
- Authentication Mockup
- Forum Mockup
- Game Reviews Mockup
- Games Page Mockup
- Group Page Mockup
- Home Page Mockup
- Profile Page Mockup
- Unregistered User Scenario: Sign Up
- Unregistered User Scenario: Search for a Game and Browse the Game Forum
- Registered User Scenario: Create Post in a Game Forum
- Registered User Scenario: Search For Groups and Join A Group
📝 RAM
- Issue Template
- Personal Information Template
- Meeting Note Template
- Contributions Template
- API Documentation Template
API Documentation for Practice App
- Top Games
- Yugioh Card
- Hearthstone Card
- Games By User
- Game Reviews
- Games By Genre
- Games By Category
- Game Suggestions
- Esport Tournaments
- Achievement By Game Id
- Rock Paper Scissors
- Game By Deal