Task | Point Person | Date Due | Done |
---|---|---|---|
Wireframe done | Nikki | W - 8/11 | ✓ |
Logo | Caitlin | M - 8/24 | ✓ |
Element board | Olivia | M - 8/31 | ✓ |
Mockup | Nikki | M - 8/31 | ✓ |
Present to Gates | Nikki/Olivia/Clayton | M - 8/31 | ✓ |
Landing Page Buildout | Olivia & Nikki | T - 9/8 | |
Launch Landing | Clayton | TH - 9/10 |
Landing Page
- Include “coming soon” language — get copy from Jenn
- Include other sunlight project logos “visual”
About Page/section
- Include copy from Jenn
Task | Point Person | Date Due | Done |
---|---|---|---|
API endpoints doc | Clayton | M - 8/31 | |
Architecture Plan | Clayton | W - 9/16 | |
Setup for static site | Clayton | TH - 9/10 | |
Search backend infrastructure | Clayton | W - 9/30 | |
Onboard new hires | Clayton | W - 9/30 |
Task | Point Person | Date Due | Done |
---|---|---|---|
Wirestorming for result cards | Nikki | T - 8/25 | ✓ |
Wireframes done for search page and cards | Nikki |
Design Dates ☐ Wirestorming for result cards T 8/25 ☐ Wireframes done for search page and cards F 8/28 ☐ Mockups for search tool done F 9/11 ☐ Present prototype of the search tool W 9/16 ☐ Feedback incorporated into mockups F 9/18 ☐ Get feedback from senior manager F 9/18 (on front-end progress. should be early enough to actually implement changes)
Development Dates ☐ Front-end development begins M 9/21 (will continue throughout the month, ~120 hours) ☐ Data importing / indexing (cd) F 10/30
Development Dates ☐ Usability Testing Week 1–4 ☐ We have a functional website. Front-end and back-end is complete, iron clad and rock solid.
Launch Dates ☐ Launch Week 1