Bug fixes
- nearbeach-1304 RFC - Implementation start date is set to today. Should be set in 2 weeks
- nearbeach-1305 RFC - Change LEAD and Group Permissions should switch positions
- nearbeach-1306 RFC - Change Lead should be updated when groups added/removed
- nearbeach-1308 RFC - selecting non of your users groups will still allow you to go to next page
- nearbeach-1310 RFC - Implementation plan - not showing validation issues
- nearbeach-1311 RFC - Backout Plan has not validation red text
- nearbeach-1312 RFC - testplan - has not validation text
- nearbeach-1313 New Change Task : out of date should update the start/end dates
- nearbeach-1314 RFC - Start/End dates are not connected to the change task dates
- nearbeach-1315 Change Task - new change task start date should match highest end date
- nearbeach-1316 Change Task delete - no modal to confirm deletion request
- nearbeach-1328 Creating new Change Task - end date can be earlier than start date