Complete Tasks and Artifacts Supporting NASA A&A Process #86
Comments
📆 October status: Work ongoing on artifacts with drafts completed for ISA, Continuous Monitoring and Contingency Plans. ON schedule for end of January delivery. |
📆 November status: Numerous documents in draft and under review, most importantly the external partner ISA. On schedule for January delivery. |
📆 December status: In progress. On schedule |
📆 01/2024 status: Completion delayed until end of February. No impact on delivery. |
📆 02/2024 status: Work ongoing. On schedule |
All expected sub-tasks completed. |