Task 1 Project Management (milestone)
- Discuss Phase 6 scoping and ranking here
- Fixed TravisCI integration so test system works again since GitHub migrated to a new TravisCI setup
- Pulled another SEMCOG PR
- The Berkeley/LBL BEAM project is now running ActivitySim for Austin. I suggested they share their work with the team once they are ready.
Task 6 Model Developer Tutorial (milestone)
- Continued work on the Jupyter notebook recipes
Task 9 Estimation Mode (milestone)
- Updated through atwork subtours, see estimation example setting.yaml
- Now tidying up and reconciling with other branches
- Need to update the estimation notebooks to run the estimation example
Task 3 Two Zones (milestone)
- I'm going to soon build the test example so we can get started next week